Chipley Library Expansion

Visual Preliminary Plan for expanding the Chipley library.

The proposed plan for the Chipley Library Expansion expands the original 7,232 square feet library. Including: 

  • West Wing (2,600 sq. ft.)
  • North Wing (1,200 sq. ft.)
  • East Wing (2,600 sq. ft.)

In addition, eighteen new parking spaces. 

Timeline

N

January 2026

Anticipated breaking of ground for Chipley Expansion.

N

December 2025

Bidding closes for RFB for Construction on December 4th. Construction contractor will be selected at the December meeting of the Washington County Board of County Commissioners.

N

October 2025

RFB for Construction goes out for bid. Mandatory Pre-Bid Meeting for contractors on October 29th, at 10 am, at the Chipley Library. (Completed)
N

December 2024-September 2025

Finalizing architectural plans and permitting. (Completed)

N

November 2024

Melvin Engineering selected for Professional Engineering and Grant Administration for the project. (Completed)

N

September 2024

 RFPs due to Washington County for review (Completed).

N

August 2024

Requests for Proposals for Professional Engineering Services and Grant Administration were advertised. (Completed).

N

July 2024

Grant agreement for Chipley Library Expansion provided by Florida Commerce; agreement approved and signed by Washington County Board of County Commissioners (Completed).

N

February 2024

Notified by Florida Commerce that Washington County had been selected to receive $3,997,816 from the Multi-Purpose Community Facilities grant (Completed).

N

October 2023

Applied for Florida Commerce Multi-Purpose Community Facilities for Chipley Library expansion project (Completed).